Sheffield BSF Project
Main Drivers/Constraints
The BSF Programme began in 2005 and was divided into different phases over 15 years. Five local authorities were selected by the Government to lead the way for the BSF scheme. Sheffield County Council was chosen as one of these pathfinder authorities.
Sheffield BSF is one of the largest schemes in the Government funded project. The County Council selected a consortium lead by Vinci Construction, to ensure every secondary school in Sheffield is rebuilt or renewed within the next three years.
One of the schools to be rebuilt and refurbished was All Saints Catholic High School on the outskirts of Sheffield City Centre. In order to refurbish the school it was necessary to decant half of the school in to Elliott Modular’s temporary accommodation.
Project Information
- The buildings are of single storey configuration and comprise of 95 modules for a minimum rental period of 80wks.
- A single jackleg unit was also supplied to serve as a temporary reception area for the school.
FEATURES INCLUDE:
- Classroom Accommodation
- Science Laboratories
- Drama Studio
- Canteen
- Library
- Staff office
- Full voice / data and IT installation
- Covered walkway
- Specialist science labs and associated furniture
- Planning permission and building regulations submission
Benefits Achieved/Key Features
Elliott Modular also supplied and installed a covered walkway between the buildings to ensure a weather proof set up for the school.